The expressway to Budapest Liszt Ferenc International Airport is to be widened to two lanes in each direction. In a Facebook video on 11 November, Dávid Vitézy, Hungary’s minister for transport and investment, announced that the government is restarting the road’s reconstruction, which the previous government had promised for more than ten years without starting it. The government resolution was published in the Magyar Közlöny, the official gazette, the same evening. The permitting process for the existing designs starts now.
What will be built?
- Two lanes in each direction, instead of one today.
- The overpasses will be rebuilt.
- At the end of Üllői út, near the border between Budapest and Vecsés, the road and the railway will be separated onto different levels.
According to the minister, a single accident or disruption on today’s road can close it completely, stranding anyone going to or from the airport and commuters from the suburbs. Everyone who lands in Budapest and travels on by the 100E or 200E bus, by taxi or by car meets the city first on this road. “We are not showing our best face,” Vitézy said.
When does work start?
More than 300 properties have to be acquired through the compulsory purchase procedure set out in law before a contractor can begin. The minister expects the construction tender to be issued in the second half of 2027; preparatory work could start in 2028 at the earliest and the main construction in 2029. When the new road will be finished, and how traffic will run during the works, is not yet known.
What the government resolution says
According to Infostart’s summary (in Hungarian), the government continues to treat better road access to the airport as a priority investment. The resolution says that:
- the minister continues the land acquisition and site preparation already under way;
- a conditional tender to choose the contractor must be launched within 90 days of the detailed designs being ready;
- land acquisition and site preparation will need at most HUF 8 billion in 2027, and at most HUF 16.47 billion must be available in the 2028 central budget;
- the minister may commit at most HUF 24.5 billion in total in 2027–2028.
A proposal on the full cost of construction will go to the government once the bid prices are known, so that figure is not yet known.
What it means for passengers
- Nothing changes for now: the road stays as it is, and works can start in 2028 at the earliest.
- Because one accident can still close today’s road, check the road traffic before you set off and allow spare time in the journey planner.
- Departures of the 100E and 200E are on our public transport page, and taxi fares on the taxi page.
Source: Vitézy Dávid, közlekedési és beruházási miniszter (Facebook)